UNDERGROUND CONSTRUCTION
COVERS & FRAMES, UNIT TYPE


These are produced in two styles, the "Unit Type" and the "Unit Type Light".  The difference is that the "Light" type are of lighter construction, the depth being 3.75" compared with 6" for the standard Unit Type.

The "Light" types are for use in grass verges, pavement cross-overs, service roads and lay-bys only.

Keys, Joint Box No. 2 are used to remove the covers.

Frame A with Cover
 


ENGINEERING INSTRUCTIONS
LINES
UNDERGROUND
C 3905
Issue 7, May 1970

FRAMES AND COVERS FOR CARRIAGEWAY JOINTING CHAMBERS

Unit Type
Description and Standard Method of Installation and Maintenance

1. General
This Instruction describes the standard method of setting Frames and Covers, Unit Type. However, in a situation where repeated failures have been experienced or where a minimum of 24 hours setting time using High Alumina cement cannot be allowed, this method should not be used and C3907 should be followed.

2 Identification
These frames and covers are recognizable by the fact that the covers are asphalt-filled and that four bolts secure the cover to the frame section during transit and installation. The latest issues of Frames and Covers, Unit type have polythene-seated frames and can be identified, without removing the cover, by the letters 'PS' which are cast into the top centre of every side frame member.

3 Component Parts
Frames and Covers, Unit Type are made to close tolerances and their frame parts as well as covers are interchangeable.

Unit 'A' comprises:-
2 Frames and Covers, Unit, End Frames
2 Side
1 Covers

Unit 'B' comprises:-
1 Frames and Covers, Unit End Frames
2 Side
1 Covers

Unit 'C' comprises: -
2 Frames and Covers, Unit, Side Frames
1 Covers

This makes it possible to assemble frame sections to hold more than one cover.

4 Sizes
The Frame and Cover, Unit, 'A' (Fig 1), gives a clear opening 1ft 11in. x 2ft 4in. for use on carriageway manhole shafts.  Two Frames and Covers, Unit, 'B' bolted together (Fig 2), give a clear opening of 3ft 10in. x 2ft 4in. for use on JRC 12, and JBC 12 joint boxes and as a replacement for Frame and Cover, Joint Box, Carriageway, and Frame and Cover, Joint Box, Carriageway, No. 7E.

Two Frames and Covers, Unit, 'B' and a Frame and Cover, Unit, 'C' bolted together (Fig 3), give a clear opening of 2ft 9 in. x 2ft  in. for use on JRC 11, JBC 11, JRC 14, and JBC 14 joint boxes.

Fig 1. Frame and Cover, Unit, 'A'


Fig 2. Two Cover Installation


Fig 3. Three Cover Installation

5 Frames and Covers
These frames and covers incorporate features novel to normal construction and the method of installation described in this Instruction must be followed. Any departure from this method is likely to lead to premature failure; in particular, it is stressed that in no circumstances must the covers be removed from the frames or the cover bolts loosened before the installation has been completed and the concrete has set.

6 Concrete mix
The following concrete mix should be used:-
Rapid-hardening Portland cement or high-alumina cement - 1 part
Fine aggregate - 2 parts
Coarse aggregate - 3 parts

The water content should be the minimum necessary to give sufficient workability.

7 Concrete materials for installation
The coarse aggregate should consist of rounded, well graded 3/8in. down, hard natural stone. The fine aggregate should be clean, sharp, natural pit or river sand containing not more than 5% silt. The cement should be rapid-hardening Portland cement to BS12 or high-alumina cement to BS915. For replacement work high-alumina cement should be used but for new work it may be more convenient to use rapid-hardening cement. If high-alumina cement is used the precautions given in A3501 should be strictly adhered to.

When concrete or mortar is mixed manually, mixing should be done on boards or a platform, not directly on the street paving or carriageway. The platform should be large enough to allow the material to be moved completely from one position to another on the platform in the course of turning over.

Surplus or condemned materials should be removed from the working site, care being taken that no materials are left to be washed into drains or sewers.

8 General precautions to be taken before installation
The covers must on
no account be removed from their respective side frame sections before completion of installation, and before installation the following points should be checked:-

  1. Ensure that the cover bolts are fully tightened.
  2. If these bolts are loose it may be necessary to reposition the frame sections with respect to the cover, but before tightening the cover bolts check that no foreign matter has entered between the frame and cover seatings. It is essential that the cover does not project beyond the end of the frames as the frame flanges might then be broken when the frame bolts are tightened during installation.
  3. If the end frame sections have dropped below the level of the side frame members, loosen the frame bolts, level the end frame section and retighten the bolts.
9 Installation of the single-cover unit
In all cases the top of the shaft must be 8in. to 8.5in. below the carriageway surface and before any attempt at installation is made this distance should be checked. As the opening will be obscured when the frame and cover is placed in position, mark the centre lines of the frame and cover with chalk on both the cover and the surrounding carriageway or top of the man-hole roof as shown in Fig 4. Set up the shuttering on the inside of the opening, projecting between 2in. to 2.5in. above the top course of bricks. Take care not to exceed 2.5in. as the shuttering may foul the frame and cover.

Fig. 4. Positioning Frame and Cover, Unit 'A'

Remove the frame-levelling screws and replace them with the heads uppermost. Then screw down the frame-levelling screws so that the threaded portions project about 3 in. below the underside of the frame. Then carefully lower the frame and cover onto the opening, using suitable lifting gear such as a Hoist, Portable, Hand with a Chain, Sling, 4 Leg (see T & T, Mechanical Aids, B1010). Adjust the levelling screws to bring the cover level with the adjacent carriageway surface. If the frame and cover is part of a new installation, set up shuttering around the frame and cover so that the inner face of the shuttering is 6in. away from the inner vertical face of the frame. For replacement purposes this will not be necessary as the excavation will form the shuttering. Then place concrete in the space between the out-side shuttering and frame. Build up a head of concrete and then thoroughly consolidate with a Vibrator, Concrete, Electric, so that the concrete flows under and around the frame. Bring up the finished level of concrete to within 2 in. of the top of the frame. The installation must then be left undisturbed and lamped off for the following periods:-
Rapid-hardening Portland cement - 2 days
High-alumina cement - 10 hours

After these minimum times have elapsed remove the inner and outer shuttering and do any necessary making good to the concrete inside the frame with a cement mortar made with the same type of cement as that use for installation. Thoroughly clean the frame seating using a dry rag and the cover seating using a rag moistened with paraffin. When the cover seating is thoroughly clean and dry, coat it liberally with Compound No. 14.

Apply the compound to the cover seating's only. In very warm weather the compound may be sufficiently liquid to be trowelled onto the seating's. If it is not, small lumps of the compound should be placed at intervals on each seating of the upturned cover. Direct heating by means of a Torch, Propane or similar equipment will cause the compound to melt and flow evenly over the whole area of the seating.

The minimum amount of heat necessary should be used because if the compound is overheated, unpleasant fumes will be given off.

The tin containing the compound should never he heated as this can be dangerous.

Replace the cover and, except where the covers are to be bolted down, seal off the holes left by the holding-down bolts with a packing of cotton waste and cement mortar or asphalt, whichever is the most convenient. An interim reinstatement should be made but before exposing the installation to traffic a minimum period after completion of the concreting must elapse, as follows:-
Rapid-hardening Portland cement - 3 days
High-alumina cement - 24 hours

In very cold weather 5 days should be allowed for rapid-hardening Portland cement.

10 Multi Cover Installation
The covers and frame sections will be received as complete 'B' or 'C' units as shown in Fig 5 and on no account must the covers be separated from their respective frame sections. When handling the units, suitable lifting gear and a Chain, Sling, 4 Leg must be used.


 

Fig 5. Frame and Cover Units 'A', 'B' and 'C'

 

(a) 3 Cover installation. Remove the nuts and bolts from the exposed jointing faces of the side frame members and store safely for later use. As with the single cover installation, mark the centre lines on the covers and on the top of the joint box with chalk, the transverse line being the centre of the 'C' unit (see Fig 8). Set up the shuttering on the inside of the joint box with struts to prevent the shuttering bowing under the weight of the concrete. Check the cover and frame bolts as detailed in paragraph 8 and reverse the levelling screws so that their heads are uppermost and about 3 in. of the threaded portion projects below the frame. Place the 'C' unit in position, taking care not to disturb the shuttering, and adjust the levelling screws so that the unit is approximateley level with the surrounding surface. Lift each 'B' unit into position and similarly adjust the height with the levelling screws.

Insert the frame-securing bolts into the abutting frame sections and bolt the units loosely together. With the aid of a straight edge or cord line, adjust the levelling screws so that all the covers are level with the surrounding carriageway. Fully tighten the frame bolts. As detailed for a single cover installation, place concrete around the frame and, after the minimum time has elapsed, treat the cover seatings with Compound, No. 14. An outer ring of shuttering will not normally be necessary in the case of a joint box. Finish off with an interim reinstatement and, as for single cover installations, allow the appropriate period to elapse before opening up to traffic.

Fig 6. Positioning a Three Cover Installation

(b) 2 Cover installation. 2 cover installation is identical to that for 3 covers except that the 'C' unit is omitted and the transverse datum line is at the junction of the 2 'B' units.

11 Removal and replacement of covers
The covers of unit type frames are designed to slide out of the frame in either direction, parallel to the short sides of the cover, and no attempt should be made to lift them bodily except when using a suitable mechanical lifting aid. The method of removing and replacing covers by means of Keys, Lifting, Carriageway, No. 2 is described in C5901.

12 Ventilation
When ventilation is necessary (see C3901) a Frame and Cover, Unit type with a ventilated cover should be fitted.

13 Weight of frame and cover units
The weights of the respective portions are approximately as follows:-
Cover - 3cwt 10lb
Side frame member - 70lb
End frame member - 65lb

14 Bolting down covers
On roads carrying high-density fast-moving traffic, evenly and tightly bolt down all covers with the holding-down bolts provided with the unit, using a Spanner, Ring, 1/2in. x 7/16in. BSW. These bolts are of zinc-plated high-tensile steel and, if found damaged or rusty, should be replaced. For Frames and Covers, Unit Type that have a metal-frame seating, Bolts No. 33 may be used but, if replacement bolts are required for the later issues of Frames and Covers, Unit Type that have polythene-seated frames, Bolts No. 33A must be used. These bolts are 1/2in. longer than Bolts No. 33.

Difficulty in fitting the cover holding-down bolts can be avoided by cleaning the thread in the holes of the frame seating using a new bolt with a liberal application of oil before replacing the cover. Should the bolt holes be choked with silt and small stones causing the bolts to '-bottom', remove the debris via the specially provided holes on the inside edge of the frame seating. Earlier issues of Frames and Covers, Unit Type were not provided with these clearance holes and a small space should be carefully chipped away from the concrete bed immediately under the bolt holes to give the same facility.

15 Renewal of polythene seats
Replace damaged or badly worn polythene frame seating with Seats, Polythene. Remove the old seating by inserting a Gimlet, Twisted, in. near one end of the polythene. The seating attached to the gimlet may then be lifted out and the new seating pressed into position. Before replacing the cover, apply a coating of Compound No. 14 as described in paragraph 9.

16 Frames and Covers, Unit Type (Light)
These frames and covers are similar to those described in the preceding paragraphs but are of lighter construction and their use is limited to grass verges, garage crossovers, service roads and lay-bys. The method of installation is also similar, the only difference being the frame depth which in the case of the Unit Light is 3.75in. compared with 6in. for the standard Frame and Cover, Unit.

Keys, Joint Box, No. 2 (T & T, Hand Tools, K1005) may be used to remove and replace these covers.

 

 

 
BACK Home page BT/GPO Telephones Search the Site Underground
Construction
Quick Find All Telephone Systems

Last revised:

FM2